Plug Valve Series

Product drawing»

Structural drawing»

You are here: News > News Detail

Check valves at force main connection of 4" and 14" lines

2010-10-28

We are proposing to connect a 4" force main to an existing 14" force main.  Based on old design plans, the 14" force main is operating at 1,600 GPM @ 216' TDH (two submersible 130 HP pumps).  Our proposed lift station will operate at 100 GPM @ 50' TDH.  We are proposing to add two check valves on either side of the MJ at the force mains connection.  QUESTION:  Assuming the p.stations can both operate at the same time, will the check valves actually function/open up against the pressure of the opposing force main flow?  In other words, if the 14" force main is running at the aforementioned flow, will the 4" check valve open once the smaller proposed pump station is in operation?

You asking if it is possible for a pump operating at a lower pressure (50' TDH) to pump into a higher pressure (216' TDH) force main.

It should seem obvious that this will not work. The check valve will never open.

Not sure why the need for the higher pressure on the larger force main, but if you want to pump into it, you will have to have a greater pressure than the line that you are pumping into.

You have posed what seems like a simple question, but in fact, it is a complicated question:

1. You will have to evaluate the system head curve. When both pumps are operating, the system head curve will increase because of the total increase in flow. Therefore the discharge pressure of each pump should increase. If the pumps are not designed to pump against the higher head (from the combined flow), then the flow will drop off accordingly.  The magnitude of this effect depends on the system head curve.

2. The pump discharge pressure when both pumps are operating will be the common for both pumps. The pump operating point of each pump will move to the common discharge pressure point. Assuming your pumps are installed at the same elevation, the low pressure pump operating point will move over on the pump curve to the shut off head (and zero flow).

3. It is generally not good practice to rely on a check valve to hold back the pressure when you have multiple pumps. Check valves do fail and you will have a mess on your hands. Consider an automatic valve to close when the pump shuts off. There is little benefit to installing check valves in series either.

4. Consider using VFD's. The VFD's will decrease the peak flow and water hammer when the pumps start/stop.

5. The large increase in pressure when the high pressure pump operates may cause a significant water hammer and/or reverse flow that may damage a pump.

You have an error in your math. V stands for velocity, not flowrate. You also do not state the materials of construction either. The estimated velocity should be about 2.9 ft/sec.

You state 12,311 ft. to the injection point. That would be 133' past the summit on the downhill side.

One should assume that the air release valves are operating and the pipe is full.

Since you are pumping with 216' of head and your injection point is just after Point F, the static head at the injection point is 816' + 216' - 952.9 =  79.1'.

The pumping head loss across the entire pipeline is about 47'. The pumping head loss to the injection point is about 41'. The estimated headloss also depends on the materials of construction and diameter.

The pressure in the 14" line at the injection point should be 79.1' - 41' + 7.1' (static head recovered from summit) = 45.2'.

I think that you basically have the head calculation correct, the question is whether you need the 2nd check valve on each pipeline.

There is no valid reason to have redundant check valves. However, you should put block valves at the connection point to allow you to maintain each pipeline without have to shut the other pipeline down.

Specify a non-slam type of check valve.

To be correct you should. However for your project, the energy is not significant.

To PEorl. After looking back on my posts I see your are correct. 79.1' is incorrectly labeled as static head.


MORE NEWS

  • anti static, double block and bleed
  • Spark Plug location on Flathead
  • What's a critical valve
  • Check valves at force main connection of 4" and 14" lines
  • Shanghai MeiYan Yi Pump & Valve Co., Ltd.
    MeiYan Yi plug valve Contact MeiYan Yi
    Shanghai Enine Pump & Valve Co., Ltd.
    Enine plug valve Contact Enine
    Shanghai Saitai Pump & Valve CO., Lid.
    Saitai plug valve Contact Saitai
    Shanghai Fengqi Industrial Development Co., Ltd.
    FengQi plug valve Contact FengQi